A CIO Talk Network conversation with Hillard Sterling (Freeborn and Peters LLP), Charlie Troxell (Chicago Mercantile Exchange), Joseph Norton (McDonald’s Corporation), hosted by Sanjog Aul.
What the conversation established
The conversation established that project failure is rarely a technology problem. Joseph Norton cited the Standish Group finding that only 16% of large projects succeed on time and on budget, and said about 65% of project success comes from how a project is initiated, planned, and measured. Charlie Troxell of Chicago Mercantile Exchange argued that management discipline is the biggest factor, because teams abandon method for a hero mentality when panic sets in near the finish line. Hillard Sterling of Freeborn and Peters LLP said fixed price contracts guarantee an argument about scope, and described a case where a consultant’s different methodology pushed a project the customer budgeted at $10,000,000 toward $100,000,000. Troxell makes risk management an explicit role rated low, medium, or high, while Norton pushes for a signed project charter and a formal metrics program so performance history informs the next estimate.
Host Sanjog Aul talks with Hillard Sterling, a partner at Freeborn and Peters LLP; Charlie Troxell, Managing Director and Chief Technology Officer of Chicago Mercantile Exchange; and Joseph Norton, former CTO of McDonald’s Corporation, about ensuring IT project success. Sterling, Troxell and Norton examine why only a small share of large projects finish on time and on budget, and trace the causes to weak upfront planning, poor project selection, and expectations that are never set in writing. They compare fixed price contracts with ranged estimates, describe explicit risk manager and program management roles, and weigh staff augmentation against consultants. Norton and Troxell also argue that business owners, not IT alone, must stay accountable for a project’s return.
Contributors
- Hillard Sterling, Partner, Freeborn and Peters LLP
- Charlie Troxell, Managing Director and Chief Technology Officer, Chicago Mercantile Exchange
- Joseph Norton, Former CTO, McDonald’s Corporation
Host: Sanjog Aul, Founder and Host, CIO Talk Network
On this page: Key takeaways · Chapters · Explore more · Transcript
Key takeaways
- Joseph Norton, former CTO of McDonald’s Corporation, says IT project failure is a people, process, and management problem rather than a technology one. He pointed to the Standish Group figure that only 16% of large projects finish on time and on budget, and estimated that about 65% of project success comes from how a project is initiated, planned, and measured.
- Charlie Troxell, Managing Director and Chief Technology Officer of Chicago Mercantile Exchange, argues that management discipline is the single biggest factor in whether a project succeeds or fails. He said teams often hit a panic point near the finish line and abandon their methods for a hero mentality, and he wants most project time spent in planning and design rather than development.
- Hillard Sterling, a partner at Freeborn and Peters LLP, says fixed price contracts are a recipe for disaster because they guarantee an argument about project scope. He described a case where a consultant brought in late with an entirely different methodology helped push a project the customer had budgeted at $10,000,000 toward $100,000,000.
- Charlie Troxell of Chicago Mercantile Exchange makes risk management an explicit, named role on every project rather than an afterthought. He said his team produces a risk document that rates each risk low, medium, or high and assigns mitigations, staffed by someone who understands both the infrastructure and how the organization operates.
- Joseph Norton, former CTO of McDonald’s Corporation, argues that business owners, not the IT team, must stay accountable for a project’s return. He noted that the project team is gone once the system runs in production, so he pushes for a project charter signed by the business sponsor, CIO, and CFO and a formal metrics program.
- Hillard Sterling, a partner at Freeborn and Peters LLP, says the legal team and the business team must work together from square one rather than leaving lawyers in isolation. He wants tight damages and dispute resolution provisions written into the contract so parties talk internally instead of racing to the courthouse when a project starts to fail.
Chapters
- 0:00 Introduction: ensuring IT project success
- 2:56 Why most large projects still fail
- 4:47 Reducing failure with design and contracts
- 6:49 Planning and estimation over deadlines
- 10:45 Setting reasonable expectations
- 17:00 Portfolio selection and the right project
- 19:52 Prioritizing projects, a litigation example
- 23:16 Outsourcing, fixed price and single point estimates
- 32:33 Building risk management into the project
- 35:09 Four perspectives on project risk
- 48:09 Contractors versus consultants
- 56:08 Closing synthesis on art and science
Explore more
- Measuring IT Project Success
- Sizing an IT Project Complexity
- Partnering for Success in IT: A Dating Game
- Software Project Success: Beyond Flipping a Coin!
- What’s In It for Me?
- IT-OT Integration
Transcript
Introduction: ensuring IT project success 0:00
Sanjog Aul [00:00:25]:
Today’s topic, ensuring IT project success. Our guests for today’s show are Hillard Sterling, Charlie Troxell and Joseph Norton. Hillard is a partner at Freeborn and Peters LLP, a Chicago, Illinois based law firm. Hillard represents vendors, customers and consultants in technology disputes involving computer system implementation projects, outsourcing arrangements, software licensing issues and other technology related matters. Charlie Troxell is the Managing Director and Chief Technology Officer of Chicago Mercantile Exchange. He oversees the evolution of CME’s technical infrastructure and overall architectural strategy and leads 280 technologists in the company’s Advanced Technology and Electronic Trading Systems area. Joe is a seasoned Information Technology Executive, consultant and speaker. His former positions include CTO of the McDonald’s Corporation, Vice President of Corporate Technology for JPMorgan Bank and CTO of the National Transportation Exchange. Good morning, guys. Welcome to the show.
Sanjog Aul [00:01:58]:
Now how is 2015 treating everybody? Is it looking positive? Did you listen to the inaugural Mr. Bush’s show?
Hillard Sterling [00:02:05]:
I had to work most of the day. I caught some of the clips at night, but so far so good in 2015, but I must admit it’s too early to tell for sure.
Charlie Troxell [00:02:18]:
Being from Texas, I wore my black tie and boots.
Joseph Norton [00:02:23]:
And I spent my day digging a client’s project out of the garbage bag.
Sanjog Aul [00:02:29]:
Now we know that there has been always a lot of talk about why projects fail and what can be done to prevent such failures. And there has been a number of project management frameworks developed and used. Still a large percentage of IT projects and programs fail. What do you think is happening and what do you think we are missing here? Why is this still a chronic issue?
Why most large projects still fail 2:56
Joseph Norton [00:02:56]:
Well, this is Joseph Norton. Let me set a stage and quote one of the seminal studies that are continually done every couple of years here by the Standish Group. When we talk about project failures, repeatedly we see year after year statistics that more than suggest that 16%, only 16% of large projects will succeed on time and on budget. And the larger the company the more dismal the results will be. And yet historically for over, I don’t know, my 30 years in the industry, we know what goes wrong with projects. User requirements creep, schedule pressures, financial pressures, hurry up, get it done quicker, faster, cheaper, etcetera. And at times it just boggles the mind why we continue to repeat a failing history here. And I would suggest that the issues are not just project management, but a question of how projects are designed to be executed. One piece is how they’re selected. Is it a good project to do the right project etcetera? Will it have the support of the organization? And then second is just purely project execution and designing projects to succeed.
Charlie Troxell [00:04:10]:
This is Charlie. I believe that not only do I agree with Joe and his comments, but I’d like to add that what I’ve seen in the time that I’ve been involved in this has been that there is a critical point at which panic sets in typically and all methods are usually abandoned for kind of a hero, let’s just get to the finish line kind of mentality. And so I would say that management discipline is probably one of the biggest components in success or failure. If we don’t stick to a disciplined process, we’re not going to succeed.
Reducing failure with design and contracts 4:47
Hillard Sterling [00:04:47]:
Absolutely. And that 16% number is consistent with my experience and what I’ve seen out there. You cannot eliminate problems and failures. You can only reduce the chances of them happening. The way to do that as Joe said is to have a strong design upfront. You need strong communications between the parties. You need strong problem solving procedures in place. You need to have a solid framework and that may get you in that other 84%, avoid that 84% rate of failure. But you also need to have strong and tight contracts. And that’s where crisp drafting comes in. You need to have contractual protections that both parties understand, agree what they mean and that to some extent keep both parties out of the courtroom if a project starts to fail.
Sanjog Aul [00:05:46]:
Now when you mentioned about Charlie, this is when you mentioned that the management does not understand what it should be done and when they’re coming close to the finish line and they say, okay, screw everything, move on. Now the same way, even when we are trying to start a project, when we’re trying to decide whether a project should come into being, I mean, it basically comes because of two reasons. One, it could be a sacred cow. One of the top guys went to a seminar or a trade show and they listened to a cool thing about SRM or CRM or any latest and greatest thing that’s coming out there and they’ll come back and talk to their corresponding technology leader and say, let’s do this. The other thing is when they are waiting till the 11th hour and things are not getting done and then say, hey, we have to have this crash project start. Now this is not the best way for you to even initiate a project. What normally it’s said is that you have to look at the benefits, you have to look at the resources that are available and the risk that you’re going to carry if you do something at 11th hour. So what are your thoughts?
Planning and estimation over deadlines 6:49
Charlie Troxell [00:06:49]:
Well, I’ve seen two different approaches to doing projects in technology. One of them is, here’s your deadline, just get whatever done you can get done by that point. And another one is a real approach of planning and estimating and resource loading and discipline to project management and producing from that a Gantt chart approach process that allows for a real accurate estimation or as accurate as you can deliver at that point in time. Typically senior management wants things by a certain timeframe. They don’t want to take the time to go through a planning exercise. If in fact you were to load time across 4 quadrants of a project the planning stage, the design and development and implementation stages, you should have most of the time in the planning stage and the design stages and very little time left than are needed for the development and implementation. And it happens the other way around. The planning is done very quickly and then it’s off to the races. And so I’d like to see more focus on the planning and design aspects of the project with real understanding of what is to be delivered and real estimation of what time frames it can be delivered. There are tools available. There always have been tools available to allow for that. Most companies probably don’t use those. They kind of try to wing it and do best guess estimates of things. And that’s where you end up in trouble because the programmer says it looks like 3 days worth of work, but they don’t consult the QA department that says I need 3 weeks to do the regression test.
Hillard Sterling [00:08:32]:
This is Hillard Sterling. Those exact problems are the ones that keep me very busy as a litigator. Projects without upfront planning are projects that are destined for problems and perhaps even failure. That is unfortunately contradictory to the way companies like to move. They want to be the first ones on the block to have that system in place. They want to acquire a system and get it in as quickly as possible for their own internal interests and presumably they’re buying the systems to save money and to improve their bottom line. So they don’t want to wait for that. So unfortunately, the planning process usually doesn’t get the attention that it deserves. But the parties should have those systems discussed, carefully structured and negotiated. And that goes all the way back to the beginning of the process in the RFP stage. The customer and the vendor should be talking way back at the beginning about what kind of systems are going in, when and how and who’s responsible. Those RFP guarantees and assurances, which should be specific, should be put into that contract and the party should be keeping an ongoing focus on it. Unfortunately, like Charlie was saying, that doesn’t happen often.
Joseph Norton [00:09:50]:
Let me add two perspectives here that reinforce what Charlie and Hillard have just mentioned. One is a pattern of developing and starting up projects in corporations we see over and over again. And as a pattern it says it’s like a 10-step schedule, right, executive management process. One is a project is conceived targets and goals and timelines are set and then we assign staff. Staff generates task lists, everyone goes out works the projects, its elbows flying everywhere. Sooner or later somebody shows up at the end of the quarter and asks for a status and then everybody runs around to hide the bad news because we’re just not getting there. And you get a crisis point and we ask executive management for intervention, right. And then what do we do? We extend the schedules and this all points to the issue of planning and designing projects, okay. When we talk about failures, let’s put this in context.
Setting reasonable expectations 10:45
Joseph Norton [00:10:45]:
When we talk about IT projects today, it’s not like something fell out of the sky or the bus blew up on the street or something like that. This is about we fail to meet expectations of schedule and cost and what the end result of the product is delivered, okay? So it’s all about are we setting reasonable expectations. And we’ve been involved in my peer groups etcetera in studies over the years that repeatedly not just suggests point that 65% of the success in project management and supporting projects comes from how it’s initiated, how it’s planned and how we measure the performance so that we can adjust and tune the project as we go.
Sanjog Aul [00:11:25]:
So do you think that this means that we should become or like the project managers should become the pushback specialists and expectation setting specialist more than a typical IT guy?
Joseph Norton [00:11:38]:
I think the project management role should be fully professionalized and career path in organizations dependent on information technology or other project work and that we need to allow project managers to do more than one major project in their life so that they gain the experience, the consistency and experience in project management.
Sanjog Aul [00:12:00]:
And let’s talk about the different components of project proposal and planning that we see related to delivery schedule, communication and risk management. And we see that there has been a fairly good amount of expertise developed over in terms of estimations and scheduling. However, we still see the way communication goes on within project team leads and team members as well as the risk management, the way it’s carried out, it’s still in a chronic stage of evolution. It doesn’t seem to be getting there. So what is happening? How has it evolved? And what can be done about it?
Sanjog Aul [00:15:37]:
For listeners who’ve just tuned in, today’s topic is ensuring IT project success. Our guests for today’s show are Hillard Sterling, Charlie Troxell, and Joseph Norton. Hillard is a partner at Freeborn and Peters LLP, a Chicago, Illinois based law firm. Charlie Troxell is the Managing Director and Chief Technology Officer of Chicago Mercantile Exchange. And Joe is the former CTO of the McDonald’s Corporation, Vice President of Corporate Technology at JPMorgan Bank and CTO of National Transportation Exchange. Before the break, we discussed or in fact we were getting into the fact that the components of project proposal or planning include delivery schedule, communication and risk management, and we know that the delivery schedule estimation related portion is kind of under control. But communication risk management is still to be looked at, and we have to see how it evolves. But before we get into it, let’s quickly go back to our original question where we spoke about the project planning and why things are not planned properly upfront. But let’s go even a level below that. We are going to talk briefly about the fact that when we are about to choose a project, whether we should do a specific project or not, what’s the due diligence that is performed and what has not been done because of which the wrong type of project is taken on and then of course that that’s a recipe for disaster. So guys?
Portfolio selection and the right project 17:00
Joseph Norton [00:17:00]:
I thought you’d make a point about talking about project management. And if we go to the profession of project management and the Project Management Institute, our body of knowledge etcetera and talk about projects from an initiation stage to a planning to an execution and control etcetera. We define in the profession initiation as having a business case and then having a charter to plan a project etcetera. But I’d like to suggest that our definition in the industry from project management that the initiation the first step of initiation is really portfolio selection within a corporation where multiple competing investment opportunities for internal funds for technology projects come up head to head with each other for prioritization. And one of the first steps for the success of any project is, is it the right project for the corporation? And is the organization behind and supportive across the board that it’s the right project to do?
Charlie Troxell [00:18:02]:
This is Charlie. One of the challenges that I face daily here is the incoming stream of requests for things to be done. And when we put a budget together for the year, we work with our divisions that I support the products and services requirements as well as operations. And sometimes we have the exclusive or situations where we have conflicting requirements. One division wants one planning and directly conflicts with what we’re planning to do for another. That’s one challenge. Another challenge is, as always, our Board of Directors or senior management team may parachute another project in on top of all of this after the planning has been done. I suggest that and one of the words that was spoken here a couple of seconds ago, investment really isn’t considered in most of the project planning activity. They’re really in a portfolio selection needs to be a hurdle rate to be considered and will the return on this project actually surpass that hurdle rate. And if not, then we probably shouldn’t be doing it. At the same time, conflicting with all of that is a goal usually from the Technology Division, which is to keep a program underway of modernization and enhancements to the existing world. And so there’s some amount of work that always has to be done there and that sometimes conflicts as well when you’re trying to select what makes up the portfolio for the year. And in my experience over the last 35 years, I’ve never been through one year in 35 where things didn’t change in January or February from a plan that was put together in December. So we have these ongoing shifting sands and no one is really doing I think a financial analysis job or role to determine which things are really the most profitable or which ones would give the corporation the best payback for doing?
Prioritizing projects, a litigation example 19:52
Hillard Sterling [00:19:52]:
It’s Hillard Sterling. And from a litigator’s perspective, it seems obvious to me from what I’ve seen over the years that prioritizing and selecting projects is a hugely important issue. It often will spell the success or failure of not only the project that you’re focusing on, but other projects around it. I just finished litigating a case that involved an implementation project that failed largely because the CIO of the company I was suing, did a horrific job of identifying and selecting her priorities and projects when she came on board with the company. As a result, not only did the project fail that was the subject of the litigation, but all of her projects were in total disarray. We were able to discover all the documents and unearth them and present them at trial to show that that’s why the project failed. And ultimately the end of her story, at least with regard to this particular issue, is that she ended up having after all these projects went south to conduct a return on investment study to try to justify what she was doing and why internally. So in other words, she was at the very beginning of the process after many months and years and all because of her failure to do that work upfront decide what was wise investment and why.
Sanjog Aul [00:21:27]:
Now let’s go back to the fact where delivery schedule estimations and related things are still we are comfortable with in a way. The fact that communications between the team members, the stakeholders and the risk management, they are still chronic issues and they are not being coming up to our expectations. I think those are becoming the bottleneck to in terms of ensuring a project success. So how do we see these areas evolving? Are we on an improvement path? Or are we going further degradation is there because of the fact that we do mergers and acquisitions, we do outsourcing. We are, in fact, having number of level of you can say there are more levels increase in terms of communication. So are we improving in those areas? And if yes, then that’s good. But in the end case, it’s not, then what needs to be done?
Hillard Sterling [00:22:23]:
Well, this is Hillard. Just to chime in briefly, I think that the realities are that we’re not improving. Things are getting more complex and there’s an ongoing series of developing challenges for executives and project managers to face given the emergence of new technologies, new processes. There are certain things that you can get better at because they’re relatively straightforward. But this is an art, not a science. And this art work is getting increasingly layered and difficult to keep a grasp of. I don’t think that’s ever going to change. So what needs to be focused on I think is developing these kinds of systems and processes upfront that we’ve been talking about to minimize the risks.
Outsourcing, fixed price and single point estimates 23:16
Joseph Norton [00:23:16]:
Well, there’s no doubt in my mind that the execution of projects professionally within corporations today is getting worse, okay. And there’s such a penchant for finding silver bullets in easier ways to do it. And that’s what I believe personally has been behind the wave of outsourcing mania that’s gone on for the last couple of years, etcetera. It’s like, okay, I can’t deal with it inside. We’re terrible. Let me throw it outside. And projects are hard work, okay? And you look for the silver bullet, you throw it over the fence. The organizations that are engaged in taking advantage of the opportunities to make money by outsourcing work from corporations, they’re hiring from the same skill sets and people pools that the corporations are in every region in The United States and the world. So why do we think that it’s going to get better? The second piece of the complexity is that we talk about technology projects like they’re different. Years ago, we always called the technology project research and development, because we were developing the technology as we went inside corporations. Today there’s not an IT project going on in corporate America that is not being put together with technology that is brand new. It’s all off the shelf. It’s all becoming commoditized. And we wonder why technology projects fail. It’s not the technology guys. It’s the people. It’s the processes. It’s the management. And it’s the discipline to do the due diligence and the hard work of planning and executing projects. And I’m going to keep coming back and harping on the setting of expectations and budgets and estimating. I think one of the things that’s hurting us today is the movement towards all outsourced projects or contracted projects going to fixed fee contracts, putting all the risk on the contractors and assuming none of the financial risk on the part of the buyer. I’m really interested to hear, Hillard, what you might think of that on the fixed price contract realm, because when we fixed price a contract, we’re trying to ignore risk and you cannot predict the total outcome. And I think one of the biggest issues in planning projects in the estimation phase today is that they’re all single point estimates. Whatever happened to ranging of estimates, best probability, worst case probability and then managing within a bandwidth of time and schedule and finances?
Hillard Sterling [00:25:46]:
Just to react briefly to your point about fixed price, there’s no doubt. It’s a recipe for disaster. You have a fixed price contract. You have guaranteed yourself an argument about project scope.
Joseph Norton [00:25:58]:
Every time, every time.
Hillard Sterling [00:25:59]:
There’s no doubt about it. And those arguments are also the most fuzzy and difficult to resolve because they weren’t really thought about usually upfront and that’s usually why my phone rings.
Charlie Troxell [00:26:13]:
I’d like to disagree with a couple of things that Joe said. I think we are getting better at some things. And I was kind of seeing a pessimistic message there. But I believe that you can in fact I mentioned, management discipline put in processes in place. You can do range estimates. You can do Monte Carlo analysis and determine what probable results versus a single point result kind of things might be. But you have to get the user community, the recipients of all of this to agree to that. And so the negotiation comes down to are they willing to work with you on a basis of a range of dates, on a range of functionality to be delivered and so forth, are they looking for that absolute? And in all cases, I think they’re looking for the absolute. And that’s the challenge that we have as technologists is to present it as not there isn’t an absolute. There’s this range. And as you get tighter estimates and better views, you’re going to reduce that range width, but there’s still a range of delivery estimates. And I think it’s an expectation setting problem that we need to address.
Joseph Norton [00:27:21]:
Yes. Charlie, I would agree with you 100 because every organization that I see succeeds in project execution does exactly what you’re saying can be done. On a broad basis across industry, it’s not predominant.
Sanjog Aul [00:27:34]:
We talk about specifically risk management and when we talk about putting things in black and white and while we say we do it, but still there are a lot of things, there are a lot of gotchas, there are a lot of shortcomings there. So what are those and what can be the due diligence, what can be the forethought that should affect it and people should be able to manage the risk in a much better way and then put things in writing, in a best form or fashion.
Sanjog Aul [00:31:19]:
For listeners who have just tuned in, today’s topic is ensuring IT project success, and our guests for today’s show are Hillard Sterling, Charlie Troxell, and Joseph Norton. Hillard is a partner at Freeborn and Peters LLP, a Chicago, Illinois based law firm. Charlie is Managing Director and Chief Technology Officer of Chicago Mercantile Exchange and Joe is the former CTO of McDonald’s Corporation, Vice President of Corporate Technology at JPMorgan Bank and CTO of the National Transportation Exchange. Before the break, we quickly discussed about the fact that not enough black and white work is done or maybe if it’s done, then it’s not coming up to the standards that it is supposed to so that when if all things go south, then we are covered. And in fact, it’s not only for the fact that when it’s going to fail, to succeed, the setting up expectations, it’s not the legal part only, but even setting up expectations should be somewhere in writing because people can always say something when they are ever in the planning stage, yes, we’ll do this, yes, we’ll do that. But they can always go back and not take the responsibility for something not happening the way it was expected. So what is being done nowadays? And where are the shortcomings? Where are the gotchas? And what can we do about them?
Building risk management into the project 32:33
Charlie Troxell [00:32:33]:
This is Charlie. One of the things that we’ve implemented here over the last couple of years is an explicit process for a systems lifecycle here at the Chicago Mercantile Exchange. What we tried to do was basically define roles for projects. And I think Joe mentioned earlier about the professional project manager and having someone whose role is project management and not necessarily just the technology manager that happened to be hanging around the hallway and needed something to do. In those definitions of roles, we have specific activities as well as the artifacts that those activities produce. And risk management is a huge undertaking and the understanding of what risks might be involved, you need a professional risk manager who knows what to look at, what to assess and how to assess those risks and how to then suggest mitigations for those risks, those ought to be roles built into the project. There ought to be a risk manager for a project as an explicit role. There needs to be a project manager. You need to have work breakdown structures and all that stuff that comes with project management. But if you explicitly lay someone out to be the risk manager and it has these following activities and the deliverables are a risk document that outlines at every turn what the risks are and what the mitigations for those are, but not only what they are, but what the probability is that they might occur. So we’ve got a low, medium, high kind of ranging of those things and it’s been very effective for us to be able to identify things and the persons that take on those roles should have enough understanding of not only the infrastructure, but also the organization and how it operates to be able to identify what all those risks might be.
Hillard Sterling [00:34:14]:
Yes, it’s Hillard. I agree with all those points. I would add that from a legal perspective, they all need to be documented very carefully and crisply in a contract. And you can break it down into about four areas. The product, how is this product supposed to perform, what is it supposed to do, the planning, what’s the planning stage, the process and how is it going to proceed. Third, the people, who’s going to be on the project, what are their qualifications and that’s true for both the customer and the vendor. And fourth, you need to have really tight and crisp damages and dispute resolution provisions. So that if something goes wrong, you have a ladder up which you can walk, so that you’re not so nobody’s trying to win a race to the courthouse. You’re not filing a complaint. You’re talking and communicating internally and that all should be in the contract.
Four perspectives on project risk 35:09
Joseph Norton [00:35:09]:
I’d like to expand upon what Charlie and Hillard had already put on the table, which are the focus on the specific project risks or contract risk and expand that view of risk all the way to the beginning of portfolio selection. And not just suggest because these are recommendations we give to our clients today is that in the business case, right, we always hear about well you’re going to do a business case we have to have an ROI. How many business cases do we actually see in our own practices where we look at the ROI and then we have a subtraction for the risk quotient that’s associated with the business case? Looking at risk from 4 specific perspectives. One is what is the risk to the business of doing or not doing a project, i.e. address the issue upfront that there’s always a potential for the project to fail, okay? Second is obviously the project risk or technology risk which is bound inside the project. These are people, it’s timing, staffing, will the vendor show up on time so on and so forth. The third category of risk is what are the implementation support risks associated with this. Have we looked at the project as a singular project or do we recognize that every project is really a portfolio project? Every IT project doesn’t stand alone. It has a software project component, has an infrastructure project component, it has a technology operations project component and systems management component. It has an end user training and acceptance component etcetera. And is everybody lined up and are they ready to support this project there? And then the last, the last component of risk, right? You can have tremendous success at the project level and deliver the perfect project that does everything to specification a contract, but the business doesn’t get the planned return from the use of the projects. And I think we often overlook that fact that an IT project delivers a product and that the business benefits come from the use of the product once it’s put into production. And you know what the IT project team is no longer around when it’s running in production and being used by the end users to get that business returned.
Charlie Troxell [00:37:26]:
I mentioned at another venue and I saw a lot of the heads bobbing up and down as I was saying. One of the things that we can do is have the users actually responsible accountable for that justification of a project. And therefore the failure or success really isn’t an IT failure or success. It’s really a company level thing. We put in place here and in other places I’ve worked the notion of program management as program being a larger container of which many projects that support a program may fit. So you can have the success at a particular IT portion of a project and the project still fail as Joe points out because it didn’t get the business return it was supposed to. If it’s couched in terms of program management, then you have somebody at a corporate level who manages the program and make sure that things are delivered after the project is in place as they were specified. And the accountable parties for that are usually whoever claims the revenues and technology usually is the expense column in that equation.
Sanjog Aul [00:38:30]:
So when we talk about these contracts and Hillard, you must have come across situations when whenever or even Charlie and Joe is that whenever it comes down to contract, they always say let the legal take care of it. Why is that just an isolated effort? Because at the end of the day, they are the ones who are going to live with it. The legal guys can just do it only the language part, right? So what is being done in that regard? Is there not supposed to be more contribution from senior management and all the people involved other than just the legal folks?
Hillard Sterling [00:38:58]:
There certainly should be one of the greatest challenges in these projects, I think is to bridge what maybe a disconnect between the legal team and the business team. You need to have communication between both way early on in the project to set expectations about what is being acquired and to work through all those different areas that we’ve been talking about from the product to the planning to the process and all the issues that go into creating the structure of these projects. Right now though, you often see the legal team operating in isolation, the in house lawyer negotiating the contract, handing off to the business people and then usually not getting involved unless and until and unfortunately when a problem arises. And the problem will arise if the business people are doing things that were not being communicated with and the lawyer and were not being managed and overseen by the lawyer. So I think companies need to have the lawyers and the business people together from square one communicating throughout the course of a project, developing creative and strategic ways to get beyond problems.
Sanjog Aul [00:40:15]:
So one another question that we see or in fact issue that comes up usually is that when we start a project, guess what, there are a lot of Pizza and Coke sessions and there’s a lot of fanfare, people start talking about, oh, we’ll achieve this and we’ll achieve that. And as soon as that’s done, people go back to their own work and then that whole stakeholder zeal fizzles out and they’re supposed to I mean, ideally, they’re supposed to be vigilant of what’s going on. But guess what? The project manager ends up getting the whole load of what’s going on. He’s just supposed to come and send a status report, which is hardly ever read. So this thing actually takes away the proactive management from what should be there and that kind of that could have prevented risk. But now that nobody is looking at project managers and the status quo, that’s the best he can do. Now he cannot grab anybody by the call and say, hey, this is what’s happening. So this is going to be further this is actually further reducing the success rate. So what are your thoughts about this?
Charlie Troxell [00:41:21]:
This is Charlie. One of the things that you have to try to do is you have to try to enlist not only the support of the owners or the business owners or the users of the product, the system that you’re trying to deploy, but you have to get them some skin in the game. They have to be responsible and accountable for its ultimate delivery and success. And therefore, they need to stay plugged in. In the old waterfall approaches to systems development, the users came in at the beginning, they gave you a bunch of requirements, they left and then at the end of the project you presented here it is and they either accept it or they didn’t. And in the modern model, it has to be process based not function based and therefore what you have to do is include roles for the user community and keep them involved and that will keep the team together. There has to be this project team notion. As you said, pizza and Coke at the beginning and then we’ll see you later, it can’t work. It has to be an ongoing weekly or even daily in some cases activity around the project success and that has to include the user community and the owners.
Joseph Norton [00:42:25]:
Let me add on to what Charlie is saying here. In that practice going from say the selection in the business case, I always like to see the interim step of a project charter as separate and distinct from what is the project plan and the charter being the authorization given to and the authority and power to a project manager to actually form a team and plan the project and a practice that I like to see implemented to actually drive that commitment of management team and users is to actually have the business sponsor, the CIO and the CFO of an organization sign handwritten signature on a project charter, assigning the project manager and defining his role, scope and authority in the project. And it sounds hokey, but how many times do you actually see signatures on project plans or project charters or business cases? And when you actually take that step, suddenly it becomes very personal to the people involved in supporting that project.
Hillard Sterling [00:43:28]:
If those steps were taken, you need me a lot less often.
Sanjog Aul [00:43:32]:
And let’s quickly talk about the fact that legal agreements are very important, but at the same time, there’s something beyond that we could do to make sure, especially in case of when you’re using third party services or consulting services, so that you can minimize the risk exposure and also at the same time get the best bang for the buck around them.
Sanjog Aul [00:47:12]:
For listeners who just tuned in, today’s topic is ensuring IT project success. Our guests for today’s show are Hillard Sterling, Charlie Troxell, and Joseph Norton. Hillard is a partner at Freeborn and Peters LLP, a Chicago based law firm. Charlie is the Managing Director and Chief Technology Officer for Chicago Mercantile Exchange and Joe is the former CTO of McDonald’s Corporation, Vice President of Corporate Technology for JPMorgan Bank and CTO of the National Transportation Exchange. Before the break, we went into an area where the consulting services are being used and beyond the legal agreements, which are very, very important, there has to be something which could be done from the non legal folks, actually the project stakeholders and the project members to make sure that they are able to get the best bang for the buck from the consulting services being provided and also minimize the risk exposure. So go ahead, Guy.
Hillard Sterling [00:48:04]:
Well, I’d like to talk about the legal risk, but before that maybe hear from the business side.
Contractors versus consultants 48:09
Charlie Troxell [00:48:09]:
This is Charlie. I think there’s two forms that this usually takes. One is a staff augmentation, which I call contractors that is bringing in more hands and feet to do a project. And we typically do that in roles where we need additional programmers or developers or quality assurance testers versus consultants, which you’re bringing in for a different purpose, which is that either getting some knowledge out of their head that you don’t have or having some expertise that the organization doesn’t currently have that it needs on a short term basis. So I think there’s two different approaches that you take. You can have a standard contracting agreement, which really covers hiring practices and lots of other stuff. Then those folks that are under that contract basically come in and basically have to work your process. There is no question about doing it their way versus doing it your way. So it makes it very clear and easy to understand. The other one is a little more of a challenge and I think that’s where we should spend some time discussing and that is the consulting side where someone may have a different perspective, a different view, try to enact a different approach than your normal approach.
Joseph Norton [00:49:20]:
My perspective on contracts is that there’s no easy way to do contracts. And I think one of the worst practices, and it’s not you don’t see this everywhere, but you see it enough across a lot of companies, organizations and industries is that you find the IT organization leading in contract negotiations. And I’ve always been a believer in that anytime you want to work on a contract whether it’s for consulting or staff augmentation or outsourcing what have it is that you actually need to put a contracting and negotiating team together and that it should always have a representative from the user community, the finance community, the IT technical community, the legal internal legal community with outside support, and it also should include a professional negotiator. If it’s one thing we don’t know how to do as a profession in IT is negotiate. And sometimes you need an independent third party. I would say at all times you should use a professional negotiator that has nothing at stake other than executing a good negotiation that results in the terms, the conditions, the scope, etcetera for a contract?
Hillard Sterling [00:50:35]:
No doubt about it. And I think that process that mindset needs to be brought to the consulting relationship as well. The consultants can play an important role sometimes critical for these projects, but they also add a new layer of risk. The most important step I believe is right upfront, contractually defining the role of the consultant. The reality is the consultant may have a very different agenda and approach to the project than the party hiring the consultant. Many times the consultants bring in entirely different methodology. I just got done litigating another case that largely failed, the project largely failed because the consultant came in toward the end, when things weren’t going well, and ensured that it was going to fail because they brought an entirely different methodology to the project. This was not documented well by any of the parties, including the customer that hired the consultant. And as a result, the cost of the project were increasing so significantly about tenfold from the customer’s perspective. In other words, the customer had budgeted that the project was going to cost approximately $10,000,000. The consultant brought a proposal and a methodology that was going to cost that customer $100,000,000. That’s quite a difference and it ensured the failure of the project. So that contracting, that careful delineation of roles and all of those people should be involved as well in defining what that consultant is coming to do and what kind of methodology or process that consultant is going to follow.
Charlie Troxell [00:52:18]:
I agree with Joe about bringing in the professionals. The problem is that that’s usually a time consuming and costly effort to do that that companies aren’t willing to expand. And what we’ve done is kind of middle ground where we have a vendor relation management team that we call them that basically does the negotiating. It has some technology input. It has some customer input. But basically they’re in the finance department. They’re part of our financial community here not part of the technology division and therefore kind of speak in the best interest of the company and we try to do it that way. But I agree professional negotiation is science and there’s many professionals out there. They probably most companies don’t deploy their method that way. I agree they probably should. But I would see it as slowing down a lot of progress if that were the case.
Joseph Norton [00:53:17]:
Yes, I agree with Charlie. I wouldn’t necessarily suggest that a negotiator is required for every contract. I mean, because then it’s like it could cost more than the contract’s worth, right? But at some point, when we start talking about large and complex projects, there’s a point for that.
Sanjog Aul [00:53:35]:
So quickly, let’s take a look at the PPR related work. That’s when it’s done. Then we have a business alignment exercise always going on. But when we do in terms of IT, we just set up the requirements upfront but never look back at that. So can we give a very quick comment on that that why is that not done? Why is this iterative comparison to the original requirements, which could themselves change based on the rapid changing environment that we see today?
Charlie Troxell [00:54:05]:
I think it’s partly we do some of that because we have traceability through our process. We have artifacts and we have the storage of those and can actually go against those. If you take a requirement down to how it got implemented and do that traceability, we also beyond that track that for how many bugs occur later. And so what was the shortcoming in either the requirements definition stages or design that caused the bug to occur. So we do take some formal analysis of that and we do a postmortem of every project when it’s finished to find out if there was something that was handled could have been handled in a better way. I think a lot of organizations try to do that. They may not have to do the best job at it. Maybe they don’t have the tools in place.
Joseph Norton [00:54:49]:
I think one of the best things any organization can do is put a little bit of effort into having, as Charlie said, having a formal metrics program in place for projects to look at the history of their projects because just being able to look at that performance history can tell you a tremendous amount about an organization’s capabilities and performance and estimating and risk management etcetera. And if you have that backing up your organizational approach to project planning and execution, it dramatically changes how you plan your project.
Sanjog Aul [00:55:21]:
On behalf of the show and our listeners, I’d like to thank you, Hillard, Charlie and Joe for sharing your experience and insights about what it takes to ensure success in IT projects.
Charlie Troxell [00:55:38]:
Always enjoy sharing experiences. I think that’s how we all learn.
Joseph Norton [00:55:42]:
As a closing comment, I’d just like to say is that while we talk a lot about failure and projects and things that go wrong etcetera, let there be no doubt that there are a number of organizations out there and professionals who do know how to deliver projects. Successful projects are being delivered every day. It would just be great for the country and the industry as a whole. It’s just to see more and more project successes rather than all the failures we see in the media and the press.
Closing synthesis on art and science 56:08
Sanjog Aul [00:56:08]:
With all said and done, ensuring success of an IT project is a blend of art and science. And here the art seems to be managing expectations of shareholders, the project team members, and even the end users as almost all have, say, an obvious agenda and say not an obvious agenda, not so obvious agenda. And the science is carefully planning and setting realistic expectations and responsibilities and even accountability of all concerns, not just at the time of kickoff but also during the project and overall on an ongoing basis because we are dealing with a moving target here. And expectations from an IT project in today’s day and age can be very well a moving target and it will take a vigilant and agile team to tame this space.